A contingency plan is prepared for what purpose?

A. To prevent all risks
B. To replace the project plan
C. To increase the project budget arbitrarily
D. To define actions to take if an identified risk occurs ✅

Correct Answer: D. To define actions to take if an identified risk occurs

Explanation

  • A contingency plan is a pre-planned response triggered when a risk materialises
  • It reduces delay in reacting.