A company wants a system in three months, but estimates show six months are needed. This is a failure of:

A. Legal feasibility
B. Schedule feasibility ✅
C. Operational feasibility
D. Technical feasibility

Correct Answer: B. Schedule feasibility

Explanation

The required delivery date cannot be met with available resources, so the schedule is infeasible.