250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is ______?

A. 300
B. 310
C. 312
D. 313 ✅

Correct Answer: D. 313

Explanation

  • Let's calculate the total work hours:
  • 250 men * 20 days * 5 hours/day = 25,000 man-hours
  • To finish the work in 10 days working 8 hours a day:
  • Let x be the number of men required:
  • x men * 10 days * 8 hours/day = 25,000 man-hours (to complete the same amount of work)
  • x * 80 = 25,000
  • x = 25,000 / 80
  • x = 312.5 (313)