120 men can do a work in 90 days,how many more men required to complete the same work in 40 days?

A. 60
B. 90
C. 120
D. 270 ✅

Correct Answer: D. 270

Explanation

  • To find how many more men are needed, we can use the formula for work:
  • Work = Men × Days text{Work} = text{Men} times text{Days} Work = Men × Days
  • Initially, 120 men can complete the work in 90 days. The total work can be represented as:
  • 120 × 90 = 10800 man-days 120 times 90 = 10800 text{ man-days}
  • Now, we need to find how many men are needed to complete the work in 40 days:
  • Required Men = 10800 40 = 270 men text{Required Men} = frac{10800}{40} = 270 text{ men}